Assetz Meru & Meadow Construction Status


Assetz Meru & Meadow Construction Status


Stay updated on the development schedule of Assetz Meru & Meadow. Assetz Group are committed to transparency and providing regular updates on the construction progress, strictly adhering to RERA-approved timeline.

As of June 2025, the project is in its initial construction phase, focusing on groundwork and foundational preparation.


RERA-Approved Construction Schedule:

Below is the detailed timeline for the construction of Assetz Meru & Meadow, as registered with RERA. This schedule outlines the estimated start and end dates for each major work phase, ensuring transparency and adherence to planned delivery.

Sub-Structure Work (Foundation & Basement)

This phase includes preparing the site and building a strong foundation for the towers.

  • Earthwork & Leveling:
    • Status: Ongoing.
    • Estimated Dates: May 15, 2025 – January 14, 2026
  • Foundation Footing Work:
    • Estimated Dates: December 15, 2025 – June 14, 2026
  • Up to Plinth Level (Ground Level):
    • Estimated Dates: January 15, 2026 – January 14, 2027
  • Sub-structure Flooring (e.g., Parking Floors):
    • Estimated Dates: December 15, 2028 – June 14, 2029
  • Retaining Walls (All types):
    • Estimated Dates: January 15, 2026 – December 14, 2026

Super-Structure Work (Building Framework)

This stage involves building the main framework of the towers, including columns, beams, and slabs.

  • RCC or MS Framed Structure:
    • Estimated Dates: June 15, 2026 – October 14, 2028
  • Masonry Construction (Walls):
    • Estimated Dates: January 15, 2027 – April 14, 2029
  • Plastering (Inside, Outside & Ceiling):
    • Estimated Dates: February 15, 2027 – June 14, 2029
  • Basic Plumbing, Sanitary & Electrical Work:
    • Estimated Dates: February 15, 2027 – May 14, 2029
  • Dadoing, Skirting, Flooring, Tiles Work:
    • Estimated Dates: March 15, 2027 – September 14, 2029
  • Railing and Grill Fixing:
    • Estimated Dates: February 15, 2027 – April 14, 2029
  • Joinery (Doors, Windows, Ventilators):
    • Estimated Dates: July 15, 2027 – January 14, 2030

Finishing Works (Fittings & Fixtures)

The final stage involves installing all the internal and external fittings, ensuring your home is ready.

  • Electrification, Water Supply & Sanitary Finishing:
    • Estimated Dates: September 15, 2027 – September 30, 2030
  • Painting:
    • Estimated Dates: May 15, 2027 – August 30, 2030
  • Weather Proof Work (Tiles, Concrete):
    • Estimated Dates: March 15, 2027 – March 29, 2029
  • Fire Prevention & Fire Fighting Systems:
    • Estimated Dates: March 06, 2029 – March 05, 2030
  • Elevation Work:
    • Estimated Dates: December 15, 2028 – June 03, 2030
  • Internal & External Work (including Landscapes):
    • Estimated Dates: December 01, 2028 – November 30, 2030

Disclaimer: Any content mentioned in this website is for information purpose only and Prices are subject to change without notice. This website is just for the purpose of information only and not to be considered as an official website.